Read 5th paragraph
- We have processed more than 478 RFI's from bidders
- There have been an additional 484 RFI's from the JV
- the designer's unfamiliarity with MGL Ch 149a procedures and requirements
- Just the email traffic alone form DAIQ (designer) is overbearing
- Resulting coordination with the JV is more than any other 149a project in my 40 year of construction
After reading this letter, if we were to tell you that the OPM (Skanska) was seeking $785,000 in cost overruns, while the designer (DAIS) was seeking $998,060 in overruns, and one would be granted their full request and other would only have $150,000 allowed.
Which would you think got their full request?
ANSWER:
DAIQ got their full request ($998,060)
Skanska got $150,000 of their $785,000 request
Comments
https://www.google.com/amp/s/turnto10.com/amp/news/local/pawsox-pawtucket-50-year-partnership-formally-to-end-jan-31
Also hearing that the current cost overruns are in the 15 million dollar range..
It will be interesting to see if Larry and his group pick up this tab.....
The city is finishing the ballpark. What re they going to do with it if the team says it can't afford to play f they have to pick up cost over-runs? Its a better deal for the team to just fold, or redo a deal with Pawtucket or another city. What could Worcester possibly do that will get it back its $130,000,000 (maybe $145,000,000)? Nothing.
The WooSox will play hardball. Bet on that. They hold ALL of the cards.
No Worcester politician is going to admit defeat either. The cheerleading will continue. Its not their money. Expect big tax increases as the ancillary development that was supposed to raise new tax revenue on the new buildings is not happening due to the Covid situation. The only other way to raise money is to tax the existing taxpayers (that haven't fled to FL, TX or other low tax places).